Valley City (CSi)  Residents are being updated on the Valley City parking lot improvement project.

Finished is most of the concrete work in two city parking lots including the lot north of the post office and the parking lot west of the Viking Room building.

KLJ reports starting on Monday September 11, 2017, mill and overlay operations will start on the parking lot north of the post office and the parking lot west of the Viking Room building.

Also, on Monday construction will start on Veterans parking lot, that is receiving a mill and overlay and new one way and do not enter signs. The parking lot will become a one-way parking lot traveling from Central Avenue to 2nd Avenue Northeast. These parking lots will be closed while concrete work and mill and overlay work is being completed.

The three parking lots completed earlier this year have some minor repairs that will be addressed as well. Partial closures are expected to complete these fixes.

Updated maps for all parking lot closures will be posted on the City of Valley City’s website when they are taking affect.

Any questions regarding these projects should be directed to KLJ in Valley City at 845-4980.