At the Monday Feb 3, 2025, the Jamestown City Council approved a resolution to approve the construction options relating to the NDDOT Urban Reconstruction Project at what is known as the Hardee’s intersection in downtown Jamestown. (1st Av S & 10th St)
The City approved option 4, changing the intersection to a Roundabout, and the west business loop past the Dairy Queen as option B. Information from the April 2024 meeting for the two options:
U.S. 52 Reconstruction – US 52/10th Street SE Intersection Option 4 – Roundabout
U.S. 52 Reconstruction Alternative B: 5-Lane with TWLTL for west bus loop
from previous story:
Jamestown – The North Dakota Department of Transportation (NDDOT) held a public input meeting Thursday, April 18, to discuss proposed improvements to U.S. Highway 52 from Seventh Street Southeast to Fourth Avenue Southwest in Jamestown. (the “Hardees intersection & bridges)
Above video is a prerecorded presentation by the NDDOT. Below are various pieces of that describes possible alternatives. Project would occur summer of 2027. The project proposed 4 different options to redesign the “Hardee’s” intersection. . .
Jump to Options 1-4 in Video Presentation at YouTube
U.S. 52 Reconstruction Visualizations
U.S. 52/10th Street Southeast Intersection Options
U.S. 52 Reconstruction – US 52/10th Street SE Intersection Option 1 – Radial T
U.S. 52 Reconstruction – US 52/10th Street SE Intersection Option 2 – Double Crossovers
U.S. 52 Reconstruction – US 52/10th Street SE Intersection Option 3 – Displaced Left-Turns
U.S. 52 Reconstruction – US 52/10th Street SE Intersection Option 4 – Roundabout
U.S. 52 Corridor Alternatives
U.S. 52 Reconstruction Alternative B: 5-Lane with TWLTL
U.S. 52 Reconstruction Alternative C: 4-Lane with Full Intersection Access and Raised Medians
U.S. 52 Reconstruction Alternative D: 4-Lane with 3/4 Intersection Access and Raised Medians
U.S. 52 Reconstruction Alternative E: 4-Lane with Right-In Right-Out Intersection Access and Raised Median
Related Resources
Display Boards
Virtual Presentation Slides
Comment Card
Information for Highway Projects
Storm Water Brochure
Storm Water Poster Board
The project includes full roadway reconstruction of U.S. 52 from Fourth Avenue Southwest to the intersection of First Avenue South and 10th Street Southeast, replacement of U.S. 52 structures over the James River, replacement of storm sewer and lighting, and roadway re-striping on U.S. 52/First Avenue South from Seventh Street Southeast to tie Jamestown’s downtown area three-lane cross section into the project.
Representatives from the NDDOT, City of Jamestown, and SRF Consulting Group, Inc. will be on hand to answer questions and discuss concerns.
A pre-recorded presentation and other materials will be available on the NDDOT website at www.dot.nd.gov/public-input on April 18.