Jamestown  (CSi)  The Jamestown Public School Board, Monday, approved almost $1.07 million in summer maintenance projects and related costs.

The total anticipated expenditures are almost $1.07 million.

Included in the major projects are:  $490,000 roofs replacement at the Central Office building and the L-shaped section at the middle school.

$202,000 is set aside to replace the boiler at Roosevelt Elementary.

$100,000 is earmarked for a new bus garage.

$35,000 is planned for the boiler and a sewer main projects at Gussner Elemenary School, $41,500 for a kitchen renovation at Lincoln School, and $57,900 for  maintenance projects at Louis L’Amour.

$47,200 is set aside for high school exterior caulking and new pool drains, and $18,000 for maintenance at Jamestown North school,  and  the James Valley Career & Technology Center.

In other business, the School Board, passed along congratulations to Superintendent, Robert Lech, who received his Doctorate in Educational Administration from the University of Mary..