Fast-pitch Diamond Work Progressing

Jamestown, ND (KCSi-T.V. News Jun 11, 2013) — Improvements to the McElroy Park diamond number 11 are progressing.

Joan Morris, representing a group advocating updating the diamond for fast-pitch softball, told the parkboard members that the dugouts are finished and the project is about two weeks from completion.

Still left is installing the backstop support poles and the scoreboard.

The $70,000 in project cost is paid by funds from Jamestown Parks and Recreation, Jamestown Public Schools, Jamestown College and other donors as Ms. Morris said the project is close to budget..

Parks and Recreation Director Doug Hogan says Parks Department workers will assist at the ball diamond as time allows.