Bismarck (NDDOT) The Jamestown Road Diet Construction will start ,soon, with the pavement re-striping, scheduled to begin Thursday. March 25, 2021 on North Dakota Highway 52 from 8th Avenue Northwest to 8th Street South in Jamestown. (The Road Diet Project.)
The re-striping is expected to take two days.
Beginning April 6, construction starts to include the removal of stoplights, curb ramps, and other project items, with an estimated completion date of Mid-September, 2021.
The project consists of replacing temporary pavement markings, and various improvements to ADA curb ramps, sidewalks, signals, signing and lighting.
Traffic will be delayed at times during the project.
The NDDOT would like to remind motorists to slow down and use caution throughout the work zone.
For more information about construction projects and road conditions throughout North Dakota, call 511 or visit the ND Roads map at http://www.dot.nd.gov/travel-info-v2/.