Valley City, ND  (KCSi-T.V. News)  —  The Valley City Commission, Monday (Oct 15, 2012), was updated on street projects.

Chad Peterson of KLJ, told the City Commissioners, that the first phase of the 9th Avenue Northwest Paving Improvement Project is about 85% complete.

Weather permitting, the project may be completed in about two weeks, with the road ready for traffic about October 27, 2012.

The final phase of construction of the 9th Avenue Paving Reconstruction Project could start in late April or early May, 2013.

He pointed out that weather permitting other projects should be completed soon, for this street construction season.