Valley City, ND – Construction Update – Paving Improvement District 125 – 2nd Ave NE/4th St NE and 3rd St NE/3rd Ave NE Street Reconstruction

Phase 1: 2nd Ave NE continues to be closed to traffic from 2nd St NE to 5th St NE. No detour route for motorized vehicles will be provided, temporary pedestrian access routes are being provided.

Beginning Monday, August 7, 2023, work on 4th St NE will be extended east past the alley between 3rd St NE and 4th St NE. Access to properties along the alley will be provided from 3rd St NE. No access will be available from 4th St NE.  

Updated maps for all road closures will be posted on the City of Valley City’s webpage https://www.valleycity.us/engineers when they are taking affect. If you have any questions regarding the project, please contact KLJ at (701)-845-4980.

Paving Improvement District 125 – 2nd Ave NE/4th St NE and 3rd St NE/3rd Ave NE Street Reconstruction

Phase 1: 2nd Ave NE is closed to traffic from 2nd St NE to 5th St NE. The closure will remain in effect until the corridor is reconstructed, which is anticipated to be early October. No detour route for motorized vehicles will be provided, temporary pedestrian access routes will be provided along the project route for the duration of the project.

Beginning Monday, July 24, 2023, the intersection of 2nd Ave NE and 2nd St NE will be closed for utility work. This closure is anticipated to last approximately one week.

Updated maps for all road closures will be posted on the City of Valley City’s webpage https://www.valleycity.us/engineers when they are taking affect. If you have any questions regarding the project, please contact KLJ at (701)-845-4980.