Jamestown (CSi) The Spiritwood Energy Park Association Board Tuesday, heard from Spiritwood Energy Park Senior Project Manager Rich Garman with updates on the recently installed rail loop switch.
Garman says the rail loop is now in service and 60 ethanol cars were delivered the week of April 6th.
A rail loop crossing to access the Rudolph farm land west of the plant will be installed, following cash rent agreement.
About two and a half miles of the access road has been completed.
Greg Ridderbusch notes that the construction camera currently at the site will be removed at the end of this month as most of the visible construction at the site is completed.